  • Contract for construction of terminal has been given to M / s L & T Infrastructure Limited at an estimated cost of 280 crores in October, 2016.
  • Terminal Capacity: 2.24 MPTA
  • Major commodity - coal, stone chips
  • Project Start Date: October 2016
  • Project end date: May, 2019
  • Physical progress: 48.23%
  • Financial progress: ₹ 13.97 million