Submitted by admin on
- Contract for construction of terminal has been given to M / s L & T Infrastructure Limited at an estimated cost of 280 crores in October, 2016.
- Terminal Capacity: 2.24 MPTA
- Major commodity - coal, stone chips
- Project Start Date: October 2016
- Project end date: May, 2019
- Physical progress: 48.23%
- Financial progress: ₹ 13.97 million